Skip to main content

Project Details

  • Project Team: Project Manager
  • Dan Moors: Architect
  • Eidos Architects: Contractor
  • Nunn Construction:

Scope of Work​

Remodels/Additions - $15,500,000

  • Furniture, Fixtures, and Equipment - Career and Technical Education; accommodate equipment & fixtures
  • 20-classroom addition, Modular CR Bldgs, CTE
     
  • Expand Auditorium for districtwide use
  • Stadium improvements
     

Fairness Formula Projects - $1,046,483

The School Site Improvement Committee identified fairness formula projects — a list of recommended projects. The list will be prioritized and completed as budget allows. 

  • Audio / Visual - Auditorium & stage lighting - move to LED lighting with dimming capabilities
  • Fire Alarm - Safety strobes for classrooms that cannot hear warning announcements for lockdowns
  • Flooring - Replacement of carpeting throughout the building
  • Furniture, Fixtures, and Equipment
  • Gym Curtain - New center curtain for the gymnasium to split into two classrooms
  • Interior Lighting - Hallway and classroom lighting - move to LED lighting with dimming capabilities
  • Lockers - Athletic and physical education lockers (replacement)
  • Parking - Pave the overflow staff lot
  • Permanent storage for facilities, athletics, activities programs, etc.
  • Scoreboard - New four sided scoreboard for the gymnasium to be used for a variety of purposes which would have LED capabilities to project video

Facilities Audit - $165,000

  • HVAC Controls - DDC upgrades
  • Swimming Pool - component replacement / upgrade
  • Windows and Doors - Some window and door replacement at pool

Technology Infrastructure

  • Replace hardware that enables wired and wireless connections to the Internet. 

​In Progress

Remodels and Additions

  • 20 classroom addition and modular removal: Some modular classrooms removed from building footprint. Earthwork and underground utilities complete. Drilled piers, foundation formwork, and concrete pouring complete. Concrete masonry wall and structural steel ongoing. Floor slab in place on ground floor. All stairways installed. Exterior sheathing ongoing. Elevator being installed, exterior brick fascia in progress, and interior sheet rock finishing & painting in progress.
  • Career Technical Education space: Earthwork and underground utilities complete. Drilled piers, foundation formwork, and concrete pouring complete. Concrete masonry wall and structural steel ongoing. Floor slab in place on ground floor.Exterior sheathing ongoing.Interior systems being installed (auto shop exhaust system)
  • Auditorium expansion: Earthwork and drilled piers complete. Foundation complete. Grade-beams installed. Structural steel in place. Exterior framing complete. Exterior sheathing underway and air handling unit installed 

​Completed Projects

  • Purchased new custodial equipment
  • Purchased new cleaning equipment for the pool
  • Replaced hardware that enables wired and wireless connections to the Internet
  • Replaced 600 student desks
  • Purchased exterior storage container