Project Details

Project Team
Project Manager Henry Reitwiesner
Architect Eidos Architects
Contractor Nunn Construction

Scope of Work

Remodels/Additions

  • Remodel entry to improve security
Fairness Formula Projects - $680,948
The School Site Improvement Committee identified fairness formula projects — a list of recommended projects. The list will be prioritized and completed as budget allows.
  • New bleachers in main gym
  • Exterior Improvements
    • Redo the courtyard area
    • Xeriscape the front of the school
  • Replace carpet in classrooms
  • Replace all student and teacher furniture
  • Update HVAC in portables and LMC
  • Paint as needed
  • Connect the band room to the band portable **pending approval and recommendation from D20 facilities department**
  • Refurbish all bathrooms / locker rooms?
  • Install state of the art security cameras **to be reevaluated based on security upgrades as a result of passage of 3A**

Facilities Audit - $582,000

  • ADA access to field
  • Roofing overlay / replace roof
  • Replace main entry and west-side door frames & glazing

Technology Infrastructure

  • Replace hardware that enables wired and wireless connections to the Internet.

​In Progress

Fairness Formula

  • Digital Marquee: Scheduled for installation summer 2019
  • Gym projectory: Anticipated for installation summer 2019

Technology Infrastructure

  • Internal wiring: Work anticipated to be complete in July 2019

​Completed Projects

  • Roofing overlay completed and replaced windows in select locations.
  • ADA access ramp to east athletic fields installed
  • Entry remodeled to improve security
  • Courtyard improvements complete
  • New furniture installed in library and classrooms
  • Updates to library ceiling, lighting, and walls
  • Cafetorium improvements to lighting complete