Project Details

Project Manager Matt Hood

Scope of Work​

Remodels/Additions

  • Remodel entry to improve security

Fairness Formula - $342,070

The School Site Improvement Committee identified fairness formula projects — a list of recommended projects. The list will be prioritized and completed as budget allows.
  • Paint - Repair and paint interior walls
  • Interior Walls - Replace room divider - rooms 211 / 212
  • Furniture, Fixtures, and Equipment
    • Replace cafeteria tables
    • Replace desks and chairs
    • Replace coat racks and install cubbies
  • Flooring - Replace carpet
  • Audio / Visual - Replace sound systems
  • Cabinets and Countertops - Replace counter tops, sinks and cabinets
  • Redo bathrooms - flooring, stalls and fixtures
  • Windows and Doors
    • Add windows to exterior doors
    • Replace exterior doors

Technology Infrastructure

  • Replace hardware that enables wired and wireless connections to the Internet.

​In Progress

Fairness Formula

  • Flooring: Contract awarded to replace existing flooring with new carpet in hallways and classrooms. Work scheduled to occur over summer 2019
  • Classroom furniture: Order in progress and delivery scheduled to occur over summer 2019

​Work Completed

  • Replaced hardware that enables wired and wireless connections to the Internet
  • Remodeled entry to improve security
  • LVT flooring in tri-space area installed
  • Room divider between classrooms installed
  • Gym walls repainted
  • New cubbies and coathooks installed
  • Hallway repainted