Project Details

Project Manager Eldrick Hill

​Scope of Work

Remodels/Additions

  • Remodel entry to improve security

Fairness Formula Projects - $285,551

The School Site Improvement Committee identified fairness formula projects - a list of recommended projects. The list will be prioritized and completed as budget allows.

  • New carpeting throughout building
  • Furniture, Fixtures, and Equipment
    • New lunchroom / cafeteria tables
    • Resting cot for health room
  • Replace modular decks and ramps

Facilities Audit - $455,000

  • ADA access to field
  • Replace boiler

Technology Infrastructure

  • Replace hardware that enables wired and wireless connections to the Internet.

​​In Progress

Fairness Formula

  • Flooring: Contract in place for new carpet in classrooms. Work scheduled to be done over summer 2019

Technology Infrastructure

  • Internal wiring: Work anticipated to be complete in July 2019

​Completed Projects

  • New decks / ramps on modular classrooms
  • Entry remodeled to improve security